The terminal will be developed through a public-private partnership in two phases, with facilities to handle large container ships and support southern India’s export-import trade.
Highlights:
- CCEA approves a second container terminal at Kamarajar Port.
- PPP project will cost ₹4,288.26 crore, including GST.
- Kamarajar Port will separately spend an estimated ₹450 crore on dredging.
- New terminal will add annual capacity of 2 million TEUs.
- First-phase operations are scheduled from the 25th month after concession award.
- The project will have a 40-year concession, including construction.
The Cabinet Committee on Economic Affairs, chaired by Prime Minister Narendra Modi, on Wednesday approved a second container terminal at Kamarajar Port in Tamil Nadu, with an estimated project cost of ₹4,288.26 crore, including GST.
The project will be developed under a public-private partnership using the Design, Build, Finance, Operate and Transfer model. The selected concessionaire will finance the terminal, while Kamarajar Port Limited will separately bear an estimated ₹450 crore in dredging costs.
The expansion aims to meet rising demand for containerised export-import cargo from the Chennai–Ennore industrial region and southern India.
Capacity to handle larger ships
The proposed terminal will have a 900-metre berth, a width of 30 metres and a design draft of 18 metres. Its annual handling capacity will be 2 million twenty-foot equivalent units, or TEUs, a standard measure of container traffic.
It is designed to accommodate vessels carrying up to 24,346 TEUs and measuring up to 400 metres in length.
According to the government, this capability could encourage direct calls by large mainline ships, reduce reliance on overseas deep-water hubs and lower associated feeder transport costs.
Two-phase construction plan
Phase I will add capacity of 1.1 million TEUs at an estimated cost of ₹2,429.32 crore. Construction is scheduled for completion within 24 months of the concession award, with commercial operations beginning in the 25th month.
Phase II will add another 0.9 million TEUs at a cost of ₹1,858.94 crore. Full commercial operations are scheduled from the 49th month.
The concession will run for 40 years, including the 48-month construction period. A concessionaire will be selected through open global bidding.
Existing terminal nearing capacity
Kamarajar Port’s existing container terminal handled approximately 0.7 million TEUs in FY2025-26 against installed annual capacity of 0.8 million TEUs, representing utilisation of around 88 per cent.
The government said the expansion would support cargo movement for automobile, auto component, engineering, electronics and chemical manufacturers across the southern hinterland.
The project is expected to generate approximately 750 direct and indirect jobs during construction and about 800 during operations.
Aligned with Maritime India Vision 2030 and Maritime Amrit Kaal Vision 2047, the terminal is intended to strengthen the port’s role as an East Coast trade gateway and improve maritime logistics efficiency.